7.2 Determine Budget

 

Back to Process Group Mappings

7.2 Determine Budget

The process of aggregating the estimated costs of the project activities or work packages to establish an authorized cost baseline.

 

Simple Version: Add up all the estimated costs to create project total.

PMI

 

Agile

PMBOK, Agile Difference, Comment

Inputs

Activity cost estimates

Basis of estimates

Scope baseline

Project schedule

Resource calendars

Contracts

Organizational process assets

 

Tools and Techniques

Cost aggregation

Reserve analysis

Expert judgement

Historical relationships

Funding limit reconciliation

 

Outputs

Cost performance baseline

Project funding requirements

Project document updates

 

Inputs

Activity cost estimates / Story Estimates

Basis of estimates

Scope baseline

Project schedule

Resource calendars

Contracts

Organizational process assets

 

Tools and Techniques

Cost aggregation

Reserve analysis

Expert judgement

Historical relationships

Funding limit reconciliation

 

Outputs

Cost performance baseline

Project funding requirements

Project document updates

 

The process of adding all the individual component costs together to create an overall budget. Initially it is unlikely that all the candidate features or stories for the project will be identified. So merely adding the estimates for the known stories together will give an estimate that is unreasonably low.  Initial estimates should be based more on traditional estimation approaches (like expert judgement, comparison to other systems, etc) or calculated from Timeboxed project burn projections if a fixed end date must be met.  

 

 

Related Posts

AI Agent Impacts on Project Management

Leading a Team That’s Part Machine: 5) AI Agent Impacts on Project Management

This is the 5th and last installment in my series about Leading a Team that’s Part Machine. The earlier articles are available here: Introduction to the series and why the future will likely include hybrid human / AI teams What constitutes a real agent and how most current ‘agents’ lack the agency to act Agent frameworks, API tokens and local AI: the infrastructure that runs agents Agentic pipelines and orchestration: getting agents to do meaningful work beyond what GenAI tools can do for us today This article explores how to integrate AI Agents into regular teamwork and their likely impacts on the future of project management.  To recap, I started my experiment by building AI agents 6 months ago to

Read More
20 years of Leading Answers

20 Years of Leading Answers

Twenty years ago today, on August 29, 2006, I published the first posts on LeadingAnswers.com. That sentence makes me feel old. I started the blog to write about leadership and agile project management, share ideas I was experimenting with, and hopefully connect with other people interested in the same things. At the time, agile was still sufficiently new that explaining it to traditional project managers was a large part of the job. My first real article was called “What has Leadership got to do with Agile Project Management?” My argument was that effective agile project management was much closer to leadership than traditional project management. It emphasized people over tasks, empowerment over control, effectiveness over efficiency, and direction over speed.

Read More