A Burn-Rate Based Estimation Tool

S_curve_title_2In my last post I suggested spending less time worrying about project metrics and more time on stakeholder concerns, so I thought a tool to simplify project tracking might be useful.

Having completed project estimating with the team, it is often necessary to convert effort estimates into cost estimates based on likely utilizations and then track actual hours billed against these projections. Today’s download is a simple burn-rate estimation tool that produces S-Curve graphs and let you track actual spend against burn-rate projections and planned budgets.

You can download the spreadsheet here:

Download estimation_and_budget_tracking.xls

The spreadsheet lets you enter likely utilizations for your team members as percentages of full time work.

S1

Here we see a list of team role and names in column A, their hourly rates in column B and project utilizations throughout the project in columns D – O. Just overwrite them with your own figures to use it yourself. Row 12 calculates the monthly costs based on the projected utilization, hourly rate and hours per day field (B13). So we are projecting we will need Mark 20% of full time in January and 90% in February. Row 13 sums a cumulative spend figure month on month. This data is then also presented as an S-Curve graph to the right of the Baseline estimate section.

S_curve_sample

Then as project spend data comes in, you can track the actuals to planned expenditures using the “Actual Hours Billed” portion of the spreadsheet. While we estimate future usage as percentages of full time work, worked billed usually arrives as hours, so the actual tracking portion of the spreadsheet takes “hours per period” as its input.

Actuals_tracking

Here we can see actual data has been entered for Jan-May. The originally planned budget expenditure for the project is depicted as the blue line S-curve, the overall budget is shown as the upper red line, and the spend-to-date is the green “Actual” figure.

Limitations
To simplify the spreadsheet I removed other costs you are likely to have on projects such as software licenses, hardware, travel expenses, etc, but these are easy to add back in if required. The data range for the green “Actual” spend figures needs updating each time you enter a new month’s worth of data.

Summary
If you do not have such tools in place I hope you find this useful. The idea is to automate the necessary, but mundane tasks of “riding the project bike” as much as possible so you can focus your time and attention on looking out for the rocks and potholes (issues and risks) down the road. 

Related Posts

AI Agent Impacts on Project Management

Leading a Team That’s Part Machine: 5) AI Agent Impacts on Project Management

This is the 5th and last installment in my series about Leading a Team that’s Part Machine. The earlier articles are available here: Introduction to the series and why the future will likely include hybrid human / AI teams What constitutes a real agent and how most current ‘agents’ lack the agency to act Agent frameworks, API tokens and local AI: the infrastructure that runs agents Agentic pipelines and orchestration: getting agents to do meaningful work beyond what GenAI tools can do for us today This article explores how to integrate AI Agents into regular teamwork and their likely impacts on the future of project management.  To recap, I started my experiment by building AI agents 6 months ago to

Read More
20 years of Leading Answers

20 Years of Leading Answers

Twenty years ago today, on August 29, 2006, I published the first posts on LeadingAnswers.com. That sentence makes me feel old. I started the blog to write about leadership and agile project management, share ideas I was experimenting with, and hopefully connect with other people interested in the same things. At the time, agile was still sufficiently new that explaining it to traditional project managers was a large part of the job. My first real article was called “What has Leadership got to do with Agile Project Management?” My argument was that effective agile project management was much closer to leadership than traditional project management. It emphasized people over tasks, empowerment over control, effectiveness over efficiency, and direction over speed.

Read More