Agile Pendentives

Agile pendentive A “Pendentive” is an architectural converter that lets you fit a domed roof on a square base. The pendentive shown in the image on the right is the yellow part.
 
When working in a traditional project management setting we often need agile pendentives that let us fit agile practices onto a traditional base. Here are some examples:

Traditional to Agile
1.    WBS –>  Prioritized Backlog. When asked to show the Work Breakdown Structure (WBS) sponsors and PMO are likely looking for a breakdown of the project deliverables. Traditional project management approaches recommend creating a WBS early in a project lifecycle after gathering requirements and defining scope.

Agile projects acknowledge this upfront design is likely to change and so deliberately go a little lighter on these definition activities, preferring to invest the time in building portions of application and arriving at agreement of functionality through feedback.

2.    Detailed Gantt Chart –> Release Plan. Detailed Gantt charts are another example of a detailed upfront design deliverable that is likely to be brittle and changing too frequently to warrant the update effort in project environments that have high levels of requirements uncertainty or technology uncertainty. It is not that we cannot create Gantt charts for agile projects – I do for some stakeholders. Rather that the time and effort required to update them is probably best used elsewhere in gaining agreement of the true business requirements.

So, instead of producing detailed Gantt charts that list tasks and do not survive contact with the reality of software projects, release plans that layout iterations and release timeframes are a more robust planning tool.



3.    Earned Value Reporting –> Velocity and Feature Based Reporting. Traditional earned value reporting shows progress against a plan at a given moment in time. It can show how far ahead or behind we are in terms of progress and spend. It can also used to estimate completion timeframes and final costs. However it is tied to the accuracy and quality of the plan we are tracking against. The phrase “The Map is Not the Territory” speaks to the issue that if reality diverges from our map or plan then we have to accept reality and draw a new map. Unfortunately the uncertainties of software projects often show us that our initial “map” was flawed. “Plan the work and work the plan” is a fine approach when your plan is solid, but a recipe for failure when change rates are high.

All the same estimate to complete, cost and schedule performance indices can be calculated by tracking Velocity (number of features/points completed per iteration) and checking these delivery rates against the total number of features. See this previous article for more details.

Summary
These are just a few traditional to agile pendentives, they let us apply agile “round” solutions to traditional “square” circumstances. The key to finding them is to look for the meaning behind the traditional request and then explain why the agile alternative is in a different format.

Often it is to address the uncertainty of original plans. Plans created when we know least about the endeavour (at the beginning of the project) are likely to be poor on software projects. This is because most software solutions are unique, intangible and hard to describe without reference to an evolving system. Agile methods make use of the learning’s gained through progressive elaboration to refine planning artifacts.

Other agile pendentives can be found in how we make decisions and approach estimating. The unique characteristics of software projects does not mean we cannot create project management deliverables, it just means they may be in a different format to better reflect their environment.

Books

PM Illustrated 2026

Beyond Agile

PMI-ACP Exam Prep

Agile Illustrated

Agile Fundamentals

PMI-ACP Workbook

Related Posts

20 years of Leading Answers

20 Years of Leading Answers

Twenty years ago today, on August 29, 2006, I published the first posts on LeadingAnswers.com. That sentence makes me feel old. I started the blog to write about leadership and agile project management, share ideas I was experimenting with, and hopefully connect with other people interested in the same things. At the time, agile was still sufficiently new that explaining it to traditional project managers was a large part of the job. My first real article was called “What has Leadership got to do with Agile Project Management?” My argument was that effective agile project management was much closer to leadership than traditional project management. It emphasized people over tasks, empowerment over control, effectiveness over efficiency, and direction over speed.

Read More
Agent Orchestration for Project Managers

Leading a Team That’s Part Machine: 4) Agent Orchestration for Project Managers

Today we explore agentic pipelines, loops and recursive self improvement (RSI) via our old friends, PMP Questions. This is article 4 in my AI agents series. Start here for an introduction, see here for an explanation of what constitutes a real agent, and here for a discussion of how I use them and running AI locally. This article gets into how to plan and manage agent work; that’s what “agent orchestration” means. As a project manager, I suspect you already have the thinking skills required. You already know why one person can’t do everything on a project. You staff a project with specialists, engage each of them in the correct piece of scope, and put reviews between the stages that

Read More