Are Your Metrics Dumb or Smart?

Agile Estimates On February the 16th I will be presenting at the Calgary Software Quality Discussion Group. This was the first group I presented for when I moved to Calgary nearly 10 years ago and I am very happy to go back and talk about a topic I really care about: Project Metrics. I care not in the sense that I think they are fantastic, instead I care because I think the majority of common metrics are counter productive and misguided. Here’s the outline:

Lessons Learned in Project Metrics – Are Your Metrics Dumb or Smart?

Collecting and reporting effective metrics can be a tricky business. Einstein captured it well when he noted "Not everything that can be counted counts, and not everything that counts can be counted".

Software projects have a history of measuring irrelevant and even counter-productive progress tracking metrics. The "Hawthorne Effect" should teach us that we will influence what we measure, yet companies continue to overtly track things like hours worked and lines of code written, unaware that they send the message of valuing long hours over results, and discourage simplifications and healthy refactoring. Quite often the metrics we want to track are intangible and subjective and so people tend to shy away from them.

More fundamentally, why are we even tracking these metrics? Is it to report on what has already occurred or help steer our future course? Often an imperfect view of the future is more useful than a perfect view of the past. In the real world, rear-view mirrors are much smaller than windshields for good reason, yet the accuracy of hind-sight and our attraction to certainty often creates too much of an emphasis on lagging, already occurred measurements compared to leading metrics. So we get fancy graphs of project spend and defect rates, but no better insights into what we should be doing differently in order to meet our goal.

In this presentation I will review many common project metrics and explain why they are largely misguided and counter productive. An alternative set of "Design Factory" metrics will be presented that are "simple and relevant to the true project goal", these metrics leverage the Hawthorne effect and focus on leading metrics to support smarter decision making.
 

Registration Link

Books

PM Illustrated 2026

Beyond Agile

PMI-ACP Exam Prep

Agile Illustrated

Agile Fundamentals

PMI-ACP Workbook

Related Posts

20 years of Leading Answers

20 Years of Leading Answers

Twenty years ago today, on August 29, 2006, I published the first posts on LeadingAnswers.com. That sentence makes me feel old. I started the blog to write about leadership and agile project management, share ideas I was experimenting with, and hopefully connect with other people interested in the same things. At the time, agile was still sufficiently new that explaining it to traditional project managers was a large part of the job. My first real article was called “What has Leadership got to do with Agile Project Management?” My argument was that effective agile project management was much closer to leadership than traditional project management. It emphasized people over tasks, empowerment over control, effectiveness over efficiency, and direction over speed.

Read More
Agent Orchestration for Project Managers

Leading a Team That’s Part Machine: 4) Agent Orchestration for Project Managers

Today we explore agentic pipelines, loops and recursive self improvement (RSI) via our old friends, PMP Questions. This is article 4 in my AI agents series. Start here for an introduction, see here for an explanation of what constitutes a real agent, and here for a discussion of how I use them and running AI locally. This article gets into how to plan and manage agent work; that’s what “agent orchestration” means. As a project manager, I suspect you already have the thinking skills required. You already know why one person can’t do everything on a project. You staff a project with specialists, engage each of them in the correct piece of scope, and put reviews between the stages that

Read More